Project QuickStart:
Business-Centric Methodology (BCM) Schedule
Enterprise Project Example
| WBS | Name
|
Duration | Start_Date | Finish_Date |
|---|---|---|---|---|
| 1 | Overall Project Planning
|
233 days | Sep 11 '03 | Aug 3 '04 |
| 1.1 | Project Scope
|
97 days | Sep 11 '03 | Jan 23 '04 |
| 1.1.1 | Objectives and Scope
|
1 day | Jan 12 '04 | Jan 12 '04 |
| 1.1.2 | Document Scope and Process
|
1 day | Sep 11 '03 | Sep 11 '03 |
| 1.1.3 | MyProject Scope Definition Paper
|
1 day | Jan 23 '04 | Jan 23 '04 |
| 1.2 | Identify Stakeholders and "Get Everyone
On Board"
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.2.1 | Identify Internal Staffing
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.2.2 | Identify External Stakeholders with
Roles and Responsibilities
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.3 | Overall Compliance /Requirements
|
143 days | Sep 22 '03 | Apr 7 '04 |
| 1.3.1 | Identify Compliance
Criteria/Requirements
|
1 day | Sep 22 '03 | Sep 22 '03 |
| 1.3.2 | Identify Compliance Process/Metrics
|
1 day | Apr 7 '04 | Apr 7 '04 |
| 1.3.3 | Publish Compliance Criteria/Requirements
and Metrics
|
0 days | Mar 26 '04 | Mar 26 '04 |
| 1.4 | Risk Management
|
26 days | Dec 1 '03 | Jan 5 '04 |
| 1.4.1 | Identify Programmatic, Functional, and
Technical Risks
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 1.4.2 | Identify Risk Effects Analysis
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.4.3 | Develop Mitigation Strategies
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.5 | Portfolio Management
|
189 days | Nov 12 '03 | Aug 3 '04 |
| 1.5.1 | Asset Tracking
|
105 days | Nov 12 '03 | Apr 6 '04 |
| 1.5.1.1 | Gauge Content of Asset Databases
|
1 day | Nov 12 '03 | Nov 12 '03 |
| 1.5.1.2 | Draft Portfolio Reports using Available
Data
|
1 day | Nov 26 '03 | Nov 26 '03 |
| 1.5.1.3 | Inventory and Investment Tool(s)
acquired
|
0 days | Dec 30 '03 | Dec 30 '03 |
| 1.5.1.4 | Deliver Preliminary System Portfolio
Analysis Baseline
|
0 days | Dec 30 '03 | Dec 30 '03 |
| 1.5.1.5 | Baseline the Application Life Cycle
Strategy
|
1 day | Jan 30 '04 | Jan 30 '04 |
| 1.5.1.6 | Implement Application Life Cycle Program
|
1 day | Apr 6 '04 | Apr 6 '04 |
| 1.5.2 | Budget Formulation (assumes no discrete
MyProject Spend Plan)
|
86 days | Apr 5 '04 | Aug 3 '04 |
| 1.5.2.1 | Develop MyProject Budget/Spend Plan
Guidance
|
1 day | Apr 9 '04 | Apr 9 '04 |
| 1.5.2.2 | Component Leads Monitor Spend Plan
Development
|
1 day | Apr 5 '04 | Apr 5 '04 |
| 1.5.2.3 | Component Leads Report Spend Plan Status
to MyProject
|
0 days | Aug 3 '04 | Aug 3 '04 |
| 1.6 | Strategic Communications and Change
Management
|
106 days | Jan 5 '04 | May 31 '04 |
| 1.6.1 | Portal & Collaboration
Tools/Techniques
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.6.2 | Training
|
106 days | Jan 5 '04 | May 31 '04 |
| 1.6.2.1 | Develop Training Strategy
|
1 day | May 27 '04 | May 27 '04 |
| 1.6.2.2 | Finalize Education and Training Plan
|
1 day | May 31 '04 | May 31 '04 |
| 1.6.2.3 | Develop Materials for distribution
(online, CD, etc.)
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.6.3 | Community of Interest (CoI) Functional
Support - attend meetings, provide presentations, etc.
|
6 days | Jan 5 '04 | Jan 12 '04 |
| 1.6.3.1 | CoI Planning
|
6 days | Jan 5 '04 | Jan 12 '04 |
| 1.6.3.1.1 | Objectives and Scope
|
1 day | Jan 12 '04 | Jan 12 '04 |
| 1.6.3.1.2 | Establish Linkages
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.6.3.1.2.1 | Stakeholders Set #1
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.6.3.1.2.2 | Stakeholders Set #2
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.6.3.1.2.3 | Stakeholders Set #3
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.6.3.1.2.4 | Stakeholders Set #4
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 1.6.3.1.2.5 | Stakeholders Set #n
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 2 | Information Services
|
221 days | Dec 1 '03 | Oct 4 '04 |
| 2.1 | Information Architecture Planning (not
including MyProject project content)
|
1 day | Apr 9 '04 | Apr 9 '04 |
| 2.1.1 | Document Process and Vision
|
1 day | Apr 9 '04 | Apr 9 '04 |
| 2.1.2 | Document Published
|
0 days | Apr 9 '04 | Apr 9 '04 |
| 2.2 | Conceptual Information Model
|
167 days | Feb 13 '04 | Oct 4 '04 |
| 2.2.1 | All MyProjects - Facets/Subject Areas
|
1 day | Feb 13 '04 | Feb 13 '04 |
| 2.2.2 | MyProject Focus - Facets/Subject Areas
|
1 day | Feb 16 '04 | Feb 16 '04 |
| 2.2.3 | Publish Conceptual Information Model
|
0 days | Feb 16 '04 | Feb 16 '04 |
| 2.2.3.1 | Initial Draft
|
0 days | Feb 16 '04 | Feb 16 '04 |
| 2.2.4 | Further Refine and Identify Business
Concepts
|
1 day | Apr 19 '04 | Apr 19 '04 |
| 2.2.5 | Continuing Support
|
1 day | Oct 4 '04 | Oct 4 '04 |
| 2.3 | Address CoI Interfaces
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 2.3.1 | Describe Scenarios & Interfaces
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 2.3.2 | Events to… Workflow Sequences
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 2.3.3 | Events to… Impact On All Stakeholders
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 2.4 | Information Foundation
|
100 days | Dec 1 '03 | Apr 16 '04 |
| 2.4.1 | Develop Business Rules Base
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 2.4.2 | Develop Events base
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 2.4.3 | Develop Roles Base
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 2.4.4 | Develop Security Strategy/Matrix
|
1 day | Dec 1 '03 | Dec 1 '03 |
| 2.4.5 | Continue Information Foundation Support
|
1 day | Dec 2 '03 | Dec 2 '03 |
| 2.4.6 | Business Objects
|
78 days | Dec 31 '03 | Apr 16 '04 |
| 2.4.6.1 | Object (Atomics) Identification
|
73 days | Dec 31 '03 | Apr 9 '04 |
| 2.4.6.1.1 | Atomic #1
|
1 day | Apr 9 '04 | Apr 9 '04 |
| 2.4.6.1.2 | Atomic #2
|
1 day | Apr 9 '04 | Apr 9 '04 |
| 2.4.6.1.3 | Atomic #3
|
1 day | Mar 8 '04 | Mar 8 '04 |
| 2.4.6.1.4 | Atomic #4
|
1 day | Feb 3 '04 | Feb 3 '04 |
| 2.4.6.1.5 | Atomic #n
|
1 day | Dec 31 '03 | Dec 31 '03 |
| 2.4.6.2 | For Each Object (Atomic) Identified
|
6 days | Apr 9 '04 | Apr 16 '04 |
| 2.4.6.2.1 | Identify Codelists
|
1 day | Apr 9 '04 | Apr 9 '04 |
| 2.4.6.2.2 | Develop Subset Mechanism
|
1 day | Apr 12 '04 | Apr 12 '04 |
| 2.4.6.2.3 | Develop Choice Point Criteria
|
1 day | Apr 13 '04 | Apr 13 '04 |
| 2.4.6.2.4 | Identify Authoritative Sources
|
1 day | Apr 14 '04 | Apr 14 '04 |
| 2.4.6.2.5 | Detail & Classify Facet
|
1 day | Apr 15 '04 | Apr 15 '04 |
| 2.4.6.2.6 | Develop Thesaurus
|
1 day | Apr 16 '04 | Apr 16 '04 |
| 3 | Develop Solution Scenarios
|
161 days? | Sep 5 '03 | Apr 16 '04 |
| 3.1 | Solution Scenario Planning
|
5 days | Sep 5 '03 | Sep 11 '03 |
| 3.1.1 | Objectives and Scope
|
1 day | Sep 5 '03 | Sep 5 '03 |
| 3.1.2 | Document process
|
1 day | Sep 11 '03 | Sep 11 '03 |
| 3.2 | Sunset
|
2 days | Jan 5 '04 | Jan 6 '04 |
| 3.2.1 | Operational/Functional Views
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 3.2.2 | Services/System Views
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 3.2.3 | Technical Views
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 3.2.4 | Address Sunset Issues
|
1 day | Jan 6 '04 | Jan 6 '04 |
| 3.3 | Policy Change
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.3.1 | Business Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.4 | Process/Organizational Improvement
|
20 days | Mar 5 '04 | Apr 1 '04 |
| 3.4.1 | Information Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.4.2 | Business Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.4.3 | Operational/Functional Views
|
20 days | Mar 5 '04 | Apr 1 '04 |
| 3.4.4 | Services/System Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.4.5 | Technical Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.5 | Outsourcing
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.5.1 | Information Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.5.2 | Business Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.5.3 | Operational/Functional Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.5.4 | Services/System Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.5.5 | Technical Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.6 | Modification of Existing Procurement
|
2 days | Mar 5 '04 | Mar 8 '04 |
| 3.6.1 | Information Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.6.2 | Business Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.6.3 | Operational/Functional Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.6.4 | Services/System Views
|
1 day | Mar 8 '04 | Mar 8 '04 |
| 3.6.5 | Technical Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.6.6 | Prepare for Integration
|
1 day | Mar 8 '04 | Mar 8 '04 |
| 3.7 | Modification of Existing System (Upgrade)
|
31 days | Mar 5 '04 | Apr 16 '04 |
| 3.7.1 | Information Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.7.2 | Business Services Extension
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.7.3 | Operational/Functional Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.7.4 | Services/System Views
|
1 day | Apr 16 '04 | Apr 16 '04 |
| 3.7.5 | Technical Views
|
1 day | Mar 5 '04 | Mar 5 '04 |
| 3.7.6 | Prepare for Integration
|
1 day | Apr 16 '04 | Apr 16 '04 |
| 3.8 | New Acquisition Solution
|
150 days? | Sep 5 '03 | Apr 1 '04 |
| 3.8.1 | Conduct Analysis of Alternatives (AoA)
|
150 days | Sep 5 '03 | Apr 1 '04 |
| 3.8.1.1 | Develop Tactics for AoA Effort
|
1 day | Sep 5 '03 | Sep 5 '03 |
| 3.8.1.1.1 | Objectives and Scope
|
1 day | Sep 5 '03 | Sep 5 '03 |
| 3.8.1.2 | Produce AoA Plan
|
9 days | Jan 5 '04 | Jan 15 '04 |
| 3.8.1.2.1 | Technology Maturity
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 3.8.1.2.2 | Technical Risk
|
1 day | Jan 6 '04 | Jan 6 '04 |
| 3.8.1.2.3 | Critical Technologies
|
1 day | Jan 7 '04 | Jan 7 '04 |
| 3.8.1.2.4 | Demonstration Needs
|
1 day | Jan 8 '04 | Jan 8 '04 |
| 3.8.1.2.5 | Product Functionality
|
9 days | Jan 5 '04 | Jan 15 '04 |
| 3.8.1.2.5.1 | Analyze Market
|
5 days | Jan 9 '04 | Jan 15 '04 |
| 3.8.1.2.5.1.1 | Module #1
|
1 day | Jan 9 '04 | Jan 9 '04 |
| 3.8.1.2.5.1.2 | Module #2
|
1 day | Jan 12 '04 | Jan 12 '04 |
| 3.8.1.2.5.1.3 | Module #3
|
1 day | Jan 13 '04 | Jan 13 '04 |
| 3.8.1.2.5.1.4 | Module #4
|
1 day | Jan 14 '04 | Jan 14 '04 |
| 3.8.1.2.5.1.5 | Module #n
|
1 day | Jan 15 '04 | Jan 15 '04 |
| 3.8.1.2.5.2 | Produce Product Evaluation Report
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 3.8.1.3 | Designate Source Selection Board
|
64 days | Jan 5 '04 | Apr 1 '04 |
| 3.8.1.3.1 | Selection criteria - Proposed solution
configuration
|
1 day | Apr 1 '04 | Apr 1 '04 |
| 3.8.1.3.2 | Perform AOA
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 3.8.2 | Procure Products
|
1 day? | Jan 5 '04 | Jan 5 '04 |
| 4 | Implementation
|
155 days | Jan 5 '04 | Aug 6 '04 |
| 4.1 | Further Define Scope, Business / Use /
Capability Case
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 4.2 | Document process
|
1 day | Jan 6 '04 | Jan 6 '04 |
| 4.3 | Identify Architecture Compliance
Criteria/Requirements
|
1 day | Jan 7 '04 | Jan 7 '04 |
| 4.4 | Identify Compliance Process/Metrics
|
1 day | Jan 8 '04 | Jan 8 '04 |
| 4.5 | Identify Internal Staffing &
External Stakeholders with Roles and Responsibilities
|
1 day | Jan 9 '04 | Jan 9 '04 |
| 4.6 | Review with Stakeholders
|
1 day | Jan 12 '04 | Jan 12 '04 |
| 4.7 | Review of Highest Ranking Standard
Systems
|
1 day | Jan 13 '04 | Jan 13 '04 |
| 4.8 | Site Gap Analysis and Acceptance
|
1 day | Jan 14 '04 | Jan 14 '04 |
| 4.9 | Develop Conceptual View of Interim
Solution
|
1 day | Jan 15 '04 | Jan 15 '04 |
| 4.10 | Implement Logistics Common Accounting
Processes
|
1 day | Apr 6 '04 | Apr 6 '04 |
| 4.11 | TBD (Manual vs. Automated)
|
1 day | Apr 7 '04 | Apr 7 '04 |
| 4.12 | Finalize Interim Solution & Gain
Approval
|
1 day | Apr 8 '04 | Apr 8 '04 |
| 4.13 | Solution Defined (Design/Review
Specifications)
|
8 days | Apr 9 '04 | Apr 20 '04 |
| 4.13.1 | Develop CONOPS
|
1 day | Apr 9 '04 | Apr 9 '04 |
| 4.13.2 | Define Processes & Activities
|
1 day | Apr 12 '04 | Apr 12 '04 |
| 4.13.3 | Define Business & Economic Events
(Publish & Subscribe)
|
1 day | Apr 13 '04 | Apr 13 '04 |
| 4.13.4 | Define Atomics & Constructs Per
Stakeholder/Workflow/interface
|
1 day | Apr 14 '04 | Apr 14 '04 |
| 4.13.5 | Define Attributes; Mandatory vs Optional
Codelists
|
1 day | Apr 15 '04 | Apr 15 '04 |
| 4.13.6 | Finalize Policy and Procedures Papers
for Coordination
|
1 day | Apr 13 '04 | Apr 13 '04 |
| 4.13.7 | Define Roles, Business Rules, and
Security
|
1 day | Apr 14 '04 | Apr 14 '04 |
| 4.13.8 | Draft Desk Top Procedures and Internal
Controls
|
1 day | Apr 15 '04 | Apr 15 '04 |
| 4.13.9 | Develop User Interface Specifications
including Edits
|
1 day | Apr 16 '04 | Apr 16 '04 |
| 4.13.10 | Develop any additional Reporting
Specifications
|
1 day | Apr 19 '04 | Apr 19 '04 |
| 4.13.11 | Communicate Design & other develop
other Materials
|
1 day | Apr 20 '04 | Apr 20 '04 |
| 4.13.12 | Technical Specifications Review
|
0 days | Apr 20 '04 | Apr 20 '04 |
| 4.14 | Information Integration
|
26 days | Jul 1 '04 | Aug 5 '04 |
| 4.14.1 | Analyze data conversion options
|
22 days | Jul 1 '04 | Jul 30 '04 |
| 4.14.2 | Extension Layer to Further Develop
Artifacts for Stds & Frameworks
|
4 days | Aug 2 '04 | Aug 5 '04 |
| 4.14.2.1 | Perform Industry Survey of Leading
Practices
|
1 day | Aug 2 '04 | Aug 2 '04 |
| 4.14.2.2 | Identify Demo / Solution CoI's Specific
Requirements
|
1 day | Aug 3 '04 | Aug 3 '04 |
| 4.14.2.3 | Baseline Business Artifacts for Stds
|
1 day | Aug 4 '04 | Aug 4 '04 |
| 4.14.2.4 | Baseline Required Technologies for Stds
|
1 day | Aug 4 '04 | Aug 4 '04 |
| 4.14.2.5 | Develop Guidelines / Alignments
|
1 day | Aug 5 '04 | Aug 5 '04 |
| 4.15 | Extend/Complete Information Foundation
Artifacts
|
1 day | Aug 6 '04 | Aug 6 '04 |
| 4.16 | Integration Artifacts
|
19 days | Apr 9 '04 | May 5 '04 |
| 4.16.1 | Goals - Deliverables/Outcomes - Metrics
|
1 day | Apr 9 '04 | Apr 9 '04 |
| 4.16.2 | MOA - Contract
|
1 day | Apr 12 '04 | Apr 12 '04 |
| 4.16.3 | Business Model - Application Model
|
1 day | Apr 13 '04 | Apr 13 '04 |
| 4.16.4 | Resource - User - Role
|
1 day | Apr 14 '04 | Apr 14 '04 |
| 4.16.5 | Concept - Classification - Faceted
Taxonomy
|
1 day | Apr 15 '04 | Apr 15 '04 |
| 4.16.6 | Concept - Concept (Thesaurus)
|
1 day | Apr 16 '04 | Apr 16 '04 |
| 4.16.7 | Concept - UID - Resource (Metadata)
|
1 day | Apr 19 '04 | Apr 19 '04 |
| 4.16.8 | Application Model - Integration Model
|
1 day | Apr 20 '04 | Apr 20 '04 |
| 4.16.9 | Rule - Goals and Metrics
|
1 day | Apr 21 '04 | Apr 21 '04 |
| 4.16.10 | Rule - Role - Security
|
1 day | Apr 22 '04 | Apr 22 '04 |
| 4.16.11 | Service - Component - Data - Rule
|
1 day | Apr 23 '04 | Apr 23 '04 |
| 4.16.12 | Workflow - Event - Process - Service
|
1 day | Apr 26 '04 | Apr 26 '04 |
| 4.16.13 | Pattern - Workflow
|
1 day | Apr 27 '04 | Apr 27 '04 |
| 4.16.14 | Business Line - Business Pattern
|
1 day | Apr 28 '04 | Apr 28 '04 |
| 4.16.15 | Target - External / Legacy
|
1 day | Apr 29 '04 | Apr 29 '04 |
| 4.16.16 | Message - Communications - Topology
|
1 day | Apr 30 '04 | Apr 30 '04 |
| 4.16.17 | Message - Internals (databases, etc.)
|
1 day | May 3 '04 | May 3 '04 |
| 4.16.18 | CPA -Choreography - Message
|
1 day | May 4 '04 | May 4 '04 |
| 4.16.19 | Collaboration Partner Agreements (CPA)
|
1 day | May 5 '04 | May 5 '04 |
| 4.17 | Develop Content Assembly Mechanisms
(CAM) for each Exchange
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 4.18 | Reproduce/Modify CAM for Partner
specifics (if required)
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 5 | Training
|
133 days | Jul 1 '04 | Jan 3 '05 |
| 5.1 | Analyze training options
|
1 day | Jul 1 '04 | Jul 1 '04 |
| 5.2 | Validate existing training materials for
applicability and completeness
|
1 day | Aug 31 '04 | Aug 31 '04 |
| 5.3 | Modify existing training materials
|
1 day | Nov 30 '04 | Nov 30 '04 |
| 5.4 | Develop new training
|
1 day | Dec 31 '04 | Dec 31 '04 |
| 5.5 | Provide training to users
|
1 day | Jan 3 '05 | Jan 3 '05 |
| 6 | Install, configure and implement one
solution
|
475 days | Jan 5 '04 | Oct 28 '05 |
| 6.1 | Information Conversion
|
89 days | Jul 30 '04 | Dec 1 '04 |
| 6.1.1 | Clean cut-over no data conversion
|
1 day | Jul 30 '04 | Jul 30 '04 |
| 6.1.2 | Develop data conversion process/tool
|
1 day | Oct 29 '04 | Oct 29 '04 |
| 6.1.3 | Test conversion process/tool
|
1 day | Nov 30 '04 | Nov 30 '04 |
| 6.1.4 | Convert legacy data
|
1 day | Dec 1 '04 | Dec 1 '04 |
| 6.2 | Test Plan, Data, & Testing
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 6.3 | Proof of Concept stood up
|
0 days | Jan 5 '04 | Jan 5 '04 |
| 6.4 | Monitor and evaluate solution
|
1 day | Oct 28 '05 | Oct 28 '05 |
| 6.5 | Build to Full Demonstration
|
0 days | Oct 28 '05 | Oct 28 '05 |
| 6.6 |
Analysis of Phase Out of Legacy Systems
|
1 day | Jan 5 '04 | Jan 5 '04 |
| 7 | Implement Automated Solutions
|
1 day | Mar 30 '07 | Mar 30 '07 |
| 7.1 |
Implement Internal Control, Standards & Common Processes with MyProject
& Source Systems
|
1 day | Mar 30 '07 | Mar 30 '07 |